[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274025":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},1274025,860,2,"多选题","地面石材控制工程的施工控制点的预防措施（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","对缺棱掉角的石材应挑选出来，铺装时应拉线找直，控制板块的安装边平直",true,{"key":16,"text":17,"correct":14},"B","基层在施工前一定要将落地灰等杂物清理干净",{"key":19,"text":20,"correct":14},"C","石材进场时必须进行检验与样板对照，并对石材每一块进行挑选检查，符合要求的留下，不符合要求的放在一边",{"key":22,"text":23,"correct":14},"D","石材铺装时应预铺，符合要求后正式铺装，保证干硬性砂浆的配合比和结合层砂浆的配合及涂刷时间，保证石材铺装下的砂浆饱满",{"key":25,"text":26,"correct":14},"E","石材铺装好后加强保护严禁随意踩踏，铺装时，应用水平尺检查","ABCDE","地面石材控制工程的施工控制点的预防措施：①基层在施工前一定要将落地灰等杂物清理干净。②石材进场时必须进行检验与样板对照，并对石材每一块进行挑选检查，符合要求的留下，不符合要求的放在一边。铺装前对石材与水泥砂浆交接面涂刷抗碱防护剂。③石材铺装时应预铺，符合要求后正式铺装，保证干硬性砂浆的配合比和结合层砂浆的配合及涂刷时间，保证石材铺装下的砂浆饱满。④石材铺装好后加强保护严禁随意踩踏，铺装时，应用水平尺检查。对缺棱掉角的石材应挑选出来，铺装时应拉线找直，控制板块的安装边平直。",{"id":6,"name":30,"category":31,"favorite":32},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]