[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274019":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1274019,860,2,"多选题","轻钢龙骨隔墙工程施工质量控制点的预防措施（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","按照设计图纸进行定位并做预检记录",true,{"key":16,"text":17,"correct":14},"B","检查隔墙龙骨的安装间距是否与交底相符合",{"key":19,"text":20,"correct":14},"C","龙自攻螺钉的间距控制在150mm左右，要求均匀布置",{"key":22,"text":23,"correct":24},"D","涂料的遍数一定要保证，保证涂刷均匀；控制基层含水率",false,{"key":26,"text":27,"correct":14},"E","板块之间应预留缝隙保证在5mm左右","ABCE","轻钢龙骨隔墙工程施工质量控制点的预防措施：①按照设计图纸进行定位并做预检记录。②检查隔墙龙骨的安装间距是否与交底相符合。③自攻螺钉的间距控制在150mm左右，要求均匀布置。④板块之间应预留缝隙保证在5mm左右。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]