[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274016":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},1274016,860,2,"多选题","质量控制点的重点控制对象包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","A.材料的质量与性能",true,{"key":16,"text":17,"correct":14},"B","施工方法与关键操作",{"key":19,"text":20,"correct":14},"C","易发生或常见的质量通瘸",{"key":22,"text":23,"correct":14},"D","新技术、新材料及新工艺的应用",{"key":25,"text":26,"correct":14},"E","产品质量不稳定和不合格率较高的工序应列为重点.认真分析.严格控制","ABCDE","二质量控制点的重点控制对象主要包括以下几个方面：1）人的行为；2）材料的质量与性能；3）施工方法与关键操作；4）施工技术参数；5）技术间歇；6）施工顺&mdash;万了百&mdash;募夏至或常见的质量通病；8，新技术、新材料及新工艺的应用；9）产品质量不稳定和不合格率较高的工序应列为重点，认真分析，严格控制；10）特殊地基或特种结构：对于湿陷性黄土、膨胀土等特殊土地基的处理，以及大跨度结构、、高耸结构等技术难度较大的施工环节和重要部位，均应予以特别的重视。",{"id":6,"name":30,"category":31,"favorite":32},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]