[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1274011":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1274011,860,2,"多选题","细部工程应对下列部位进行隐蔽工程验收：（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","预埋件",true,{"key":16,"text":17,"correct":14},"B","后置埋件",{"key":19,"text":20,"correct":21},"C","防水层",false,{"key":23,"text":24,"correct":21},"D","防腐",{"key":26,"text":27,"correct":14},"E","护栏与预埋件的连接节点","ABE","细部工程应对下列部位进行隐蔽工程验收：1、预埋件（或后置埋件）；2、护栏与预埋件的连接节点。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]