[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273980":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1273980,860,2,"多选题","施工图预算编制的依据有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","初步设计或扩大初步设计图纸",true,{"key":16,"text":17,"correct":14},"B","施工组织设计",{"key":19,"text":20,"correct":14},"C","现行的预算定额",{"key":22,"text":23,"correct":14},"D","基本建设材料预算价格",{"key":25,"text":26,"correct":27},"E","概算",false,"ABCD","施工图预算编制的依据有初步设计或扩大初步设计图纸；施工组织设计；现行的预算定额；基本建设材料预算价格。设计概算是在初步设计或扩大初步设计阶段，由设计单位根据初步设计或扩大初步设计图纸，概算定额、指标，工程量计算规则，材料、设备的预算单价，建设主管部门颁发的有关费用定额或取费标准等资料预先计算工程从筹建至竣工验收交付使用全过程建设费用经济文件。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]