[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273970":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1273970,860,2,"多选题","施工定额是建筑企业用于工程施工管理的定额，它由（ ）组成。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","时间定额",false,{"key":16,"text":17,"correct":18},"B","劳动定额",true,{"key":20,"text":21,"correct":14},"C","产量定额",{"key":23,"text":24,"correct":18},"D","材料消耗定额",{"key":26,"text":27,"correct":18},"E","机械台班使用定额","BDE","施工消耗定额是施工企业直接用于建筑工程投标取价、施工管理与经济核算的一种定额。它是以同一性质的施工过程或工序为测定对象，以工序定额为基础综合而成的确定建筑工人在正常的施工条件下，为完成一定计量单位的某一施工过程或工序所需人工、材料和机械台班消耗的数量标准。所以，施工消耗定额是由劳动定额、材料消耗定额和机械台班定额组成，是最基本的定额。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]