[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273963":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1273963,860,1,"单选题","主体结构工程应由（ ）组织进行验收。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目经理",false,{"key":16,"text":17,"correct":14},"B","施工单位质量负责人",{"key":19,"text":20,"correct":14},"C","设计负责人",{"key":22,"text":23,"correct":24},"D","总监理工程师",true,"主体工程属于分部工程，应当由总监理工程师或者建设单位负责人组织验收。如果工程项目委托监理的，通常由总监理工程师组织验收，没有委托监理的项目则由建设单位负责人组织验收。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]