[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273914":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1273914,860,1,"单选题","分包单位与总承包单位签订分包合同，按照分包合同的约定应对（ ）负责。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":14},"B","施工单位",{"key":19,"text":20,"correct":14},"C","发包单位",{"key":22,"text":23,"correct":24},"D","总承包单位",true,"非破坏性检验荷载下，以混凝土基材无裂缝、锚栓或植筋无滑移等宏观裂损现象，且Zmin持荷期间荷载降低不大于5%时为合格。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]