[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273799":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1273799,860,1,"单选题","下列采用喷涂法进行涂饰工程作业时，涂刷顺序正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先顶棚后墙面，墙面是先上后下，先左后右",true,{"key":16,"text":17,"correct":18},"B","先顶棚后墙面，墙面是先下后上，先左后右",false,{"key":20,"text":21,"correct":18},"C","先墙面后顶棚，墙面是先上后下，先左后右",{"key":23,"text":24,"correct":18},"D","先墙面后顶棚，墙面是先下后上，先左后右","采用喷涂法进行涂饰工程作业时，先顶棚后墙面，墙面是先上后下，先左后右。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]