[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273692":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1273692,860,1,"单选题","有防水要求的厕浴间进行防水施工，饰面层完工后应进行第二次蓄水试验，第二次蓄水试验不得低于（ ）h。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","12",false,{"key":16,"text":17,"correct":18},"B","24",true,{"key":20,"text":21,"correct":14},"C","36",{"key":23,"text":24,"correct":14},"D","48","根据《建筑地面工程施工质量验收规范》（GB50209—2010）规定，有防水要求的厕浴间进行防水施工，饰面层完工后应进行第二次蓄水试验，第二次蓄水试验不得低于24h。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]