[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273689":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1273689,860,1,"单选题","厕浴间防水层施工完毕后，检查防水隔离层应采用（ ）h方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","蓄水",true,{"key":16,"text":17,"correct":18},"B","洒水",false,{"key":20,"text":21,"correct":18},"C","注浆",{"key":23,"text":24,"correct":18},"D","破坏试验","根据《建筑地面工程施工质量验收规范》（GB50209—2010）规定，厕浴间防水层施工完毕后，检查防水隔离层应采用蓄水方法，蓄水深度最浅处不得小于10mm，蓄水时间不得少于24h。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]