[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273659":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1273659,860,1,"单选题","凡属“待检点”的施工作业，施工方必须在完成施工质量自检的基础上，提前（ ）h通知项目监理机构进行检查验收，然后才能进行工程隐蔽或下道工序的施工。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","12",false,{"key":16,"text":17,"correct":14},"B","24",{"key":19,"text":20,"correct":21},"C","48",true,{"key":23,"text":24,"correct":14},"D","72","凡属“待检点”的施工作业，如隐蔽工程等，施工方必须在完成施工质量自检的基础上，提前48h通知项目监理机构进行检查验收，然后才能进行工程隐蔽或下道工序的施工。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]