[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273658":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1273658,860,1,"单选题","技术交底是施工组织设计和施工方案的具体化，施工作业技术交底的内容必须具有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可行性和可操作性",true,{"key":16,"text":17,"correct":18},"B","适用性和可操作性",false,{"key":20,"text":21,"correct":18},"C","可行性和适用性",{"key":23,"text":24,"correct":18},"D","制度性和可行性","技术交底是施工组织设计和施工方案的具体化，施工作业技术交底的内容必须具有可行性和可操作性。从建设工程项目的施工组织设计到分部分项工程的作业计划，在实施之前都必须逐级进行交底，其目的是使管理者的计划和决策意图为实施人员所理解。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]