[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273653":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1273653,860,1,"单选题","某礼堂在图纸上位于H~K的轴及⑥~⑨轴之间。该礼堂在地面找平层施工前进行基层检查，发现混凝土表面有2mm左右的裂缝。经分析研究后认为该裂缝不影响结构的安全和使用功能。地面找平层施工工艺步骤如下：材料准备一基层清理一测量与标高控制一铺找平层一刷素水泥浆结合层一养护一验收。根据背景资料，回答下列1~6问题。 根据背景资料，铺设地面找平层施工步骤错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","材料准备→基层清理",false,{"key":16,"text":17,"correct":14},"B","基层清理→测量与标高控制",{"key":19,"text":20,"correct":21},"C","铺找平层→刷素水泥浆结合层",true,{"key":23,"text":24,"correct":14},"D","养护→验收","铺设地面找平层施工步骤：材料准备→基层清理→测量与标高控制养护→验收",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]