[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273618":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1273618,860,1,"单选题","已完施工的成品保护问题和相应措施，在工程施工组织设计与计划阶段就应该在（ ）上进行考虑，防止（ ）不当或交叉作业造成相互干扰、污染和损坏。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工顺序，施工顺序",true,{"key":16,"text":17,"correct":18},"B","施工质量，施工质量",false,{"key":20,"text":21,"correct":18},"C","施工顺序，施工质量",{"key":23,"text":24,"correct":18},"D","施工质量，施工顺序","已完施工的成品保护问题和相应措施，在工程施工组织设计与计划阶段就应该在施工顺序上进行考虑，防止施工顺序不当或交叉作业造成相互干扰、污染和损坏。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]