[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273598":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1273598,860,1,"单选题","工序施工条件控制依据不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计质量标准",false,{"key":16,"text":17,"correct":14},"B","材料质量标准",{"key":19,"text":20,"correct":21},"C","人员的调度",true,{"key":23,"text":24,"correct":14},"D","机械设备技术性能标准","控制的依据主要是：设计质量标准、材料质量标准、机械设备技术性能标准、施工工艺标准以及操作规程等。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]