[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273596":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1273596,860,1,"单选题","下列关于正式验收过程的主要工作说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实地检查工程外观质量",true,{"key":16,"text":17,"correct":18},"B","对工程的使用功能进行逐个检查",false,{"key":20,"text":21,"correct":18},"C","工程质量监督机构应签署验收意见",{"key":23,"text":24,"correct":18},"D","对项目的经营情况进行盈亏平衡分析","正式验收过程的主要工作有：建设、勘察、设计、施工、监理单位分别汇报工程合同履约情况及工程施工各环节施工满足设计要求，质量符合法律、法规和强制性标准的情况；检查审核设计、勘察、施工、监理单位的工程档案资料及质量验收资料；实地检查工程外观质量，对工程的使用功能进行抽查；对工程施工质量管理各环节工作、对工程实体质量及质保资料情况进行全面评价，形成经验收组人员共同确认签署的工程竣工验收意见等",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]