[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273588":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1273588,860,1,"单选题","作业前（ ）做好交底和记录，使（ ）在明确工艺标准、质量要求的基础上进行作业。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工员、技术员，施工单位",false,{"key":16,"text":17,"correct":14},"B","施工单位，操作人员",{"key":19,"text":20,"correct":14},"C","施工单位，施工员、技术员",{"key":22,"text":23,"correct":24},"D","施工员、技术员，操作人员",true,"作业前施工员、技术员做好交底和记录，使操作人员在明确工艺标准、质量要求的基础上进行作业。为保证质量控制点的目标实现，应严格按照三检制进行检查控制。在施工中发现质量控制点有异常时，应立即停止施工，召开分析会，查找原因，采取对策予以解决。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]