[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273581":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1273581,860,1,"单选题","下列不属于施工单位的竣工验收准备工作内容的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程档案资料的验收准备",false,{"key":16,"text":17,"correct":14},"B","设备的系统联动试运行",{"key":19,"text":20,"correct":14},"C","管道安装工程的试压",{"key":22,"text":23,"correct":24},"D","出具工程保修书",true,"竣工验收准备施工单位按照合同规定的施工范围和质量标准完成施工任务后，应自行组织有关人员进行质量检查评定。自检合格后，向现场监理机构提交工程竣工验收申请报告，要求组织工程竣工预验收。施工单位的竣工验收准备，包括工程实体的验收准备和相关工程档案资料的验收准备，使之达到竣工验收的要求，其中设备及其管道安装工程等，应经过试压、试车和系统联动试运行检查记录。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]