[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273576":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1273576,860,1,"单选题","相同材料、工艺和施工条件的室外抹灰工程每（ ）应划为一个检验批。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","500～1000㎡",true,{"key":16,"text":17,"correct":18},"B","800㎡",false,{"key":20,"text":21,"correct":18},"C","600～1000㎡",{"key":23,"text":24,"correct":18},"D","1000㎡","相同材料、工艺和施工条件的室外抹灰工程每500～1000㎡应划为一个检验批，不足500㎡也应划为一个检验批。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]