[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273566":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1273566,860,1,"单选题","（ ）以使不合格的工序或最终产品（包括单位工程或整个工程项目）不流人下道工序、不进入市场。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","事前质量控制",false,{"key":16,"text":17,"correct":18},"B","事后质量控制",true,{"key":20,"text":21,"correct":14},"C","事中质量控制",{"key":23,"text":24,"correct":14},"D","全面质量控制","事后质量控制也称为事后质量把关，以使不合格的工序或最终产品（包括单位工程或整个工程项目）不流入下道工序、不进入市场。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]