[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273556":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1273556,860,1,"单选题","抹灰工程应分层进行。当抹灰总厚度大于或等于（ ）时，应采取加强措施。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20mm",false,{"key":16,"text":17,"correct":14},"B","30mm",{"key":19,"text":20,"correct":21},"C","35mm",true,{"key":23,"text":24,"correct":14},"D","40mm","抹灰工程应分层进行。当抹灰总厚度大于或等于35mm时，应采取加强措施。不同材料基体交接处表面的抹灰，应当采取防止开裂的加强措施，当采用加强网时，加强网与各基体的搭接宽度不应小于100mm。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]