[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273550":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1273550,860,1,"单选题","（ ）是施工阶段质量控制的重点。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工序的质量控制",true,{"key":16,"text":17,"correct":18},"B","材料的质量控制",false,{"key":20,"text":21,"correct":18},"C","人员的调度",{"key":23,"text":24,"correct":18},"D","设备仪器的使用","工序是人、材料、机械设备、施工方法和环境因素对工程质量综合起作用的过程，所以对施工过程的质量控制，必须以工序作业质量控制为基础和核心。因此，工序的质量控制是施工阶段质量控制的重点。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]