[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273537":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1273537,860,1,"单选题","在施工项目成本控制中，为降低材料费所采取的措施不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","制定好材料采购的计划",false,{"key":16,"text":17,"correct":14},"B","改进材料的采购、运输、保管等方面工作，减少各个环节的损耗",{"key":19,"text":20,"correct":21},"C","定期对机械设备进行保养和维护",true,{"key":23,"text":24,"correct":14},"D","合理堆放现场材料，避免和减少二次搬运和摊销损耗","在施工项目成本控制中，为降低材料费所采取的措施有合理堆放现场材料，避免和减少二次搬运和摊销损耗；改进材料的采购、运输、保管等方面工作，减少各个环节的损耗；制定好材料采购的计划",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]