[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273532":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1273532,860,1,"单选题","建设工程项目质量控制体系，一般形成（ ）的结构形态，这是由其实施任务的委托方式和合同结构所决定的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","全方位、多单元",false,{"key":16,"text":17,"correct":14},"B","全方位、立体化",{"key":19,"text":20,"correct":21},"C","多层次、多单元",true,{"key":23,"text":24,"correct":14},"D","多层次、立体化","建设工程项目质量控制体系，一般形成多层次、多单元的结构形态，这是由其实施任务的委托方式和合同结构所决定的。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)专业管理实务 岗位知识","建筑工程",0]