[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273289":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1273289,859,3,"判断题","脚手架专项施工方案中，单、双排脚手架拆除作业必须由上而下逐层进行，严禁上下同时作业，可以先将连墙件整层或数层拆除后再拆除脚手架。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"拆除作业必须由上而下逐层进行，严禁上下同时作业；连墙件必须随脚手架逐层拆除，严禁先将连墙件整层或数层拆除后再拆脚手架；分段拆除高差不应大于2步，如高差大于步，应增设连墙件加固；当脚手架拆至下部最后一根长立杆的高度（约6.5m）时，应先在适当位置搭设临时抛撑加固后，再拆除连墙件；当脚手架采取分段、分立面拆除时，对不拆除的脚手架两端，应先加设连墙件及横向斜杆加固",{"id":6,"name":21,"category":22,"favorite":23},"(装饰质量)基础知识","建筑工程",0]