[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273009":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1273009,859,2,"多选题","当事人对建设工程实际竣工日期产生争议的，竣工日期如何确定（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","建设工程经验收合格的，以验收合格之日为竣工日期",true,{"key":16,"text":17,"correct":14},"B","施工方已提交竣工验收报告，发包人拖延验收，以提交验收报告之日为竣工日期",{"key":19,"text":20,"correct":14},"C","建设工程未经竣工验收，发包人擅自使用的，以转移占有建设工程之日为竣工日期",{"key":22,"text":23,"correct":24},"D","竣工验收报告中最后一家单位盖章日为竣工日期",false,{"key":26,"text":27,"correct":24},"E","上述四项均对","ABC","当事人对建设工程实际竣工日期产生争议的，竣工日期的确定：①建设工程经验收合格的，以验收合格之日为竣工日期；②施工方已提交竣工验收报告，发包人拖延验收，以提交验收报告之日为竣工日期；③建设工程未经竣工验收，发包人擅自使用的，以转移占有建设工程之日为竣工日期。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰质量)基础知识","建筑工程",0]