[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1273004":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1273004,859,2,"多选题","施工单位提出工期索赔的目的为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","实现项目的盈利",false,{"key":16,"text":17,"correct":18},"B","免去或推卸工期延长的合同责任，规避工期罚款",true,{"key":20,"text":21,"correct":18},"C","因工期延长而造成的费用损失的索赔",{"key":23,"text":24,"correct":14},"D","延长工期",{"key":26,"text":27,"correct":14},"E","加速施工，确保工期内完成施工","BC","施工单位提出工期索赔的目的为①免去或推卸工期延长的合同责任，规避工期罚款；②因工期延长而造成的费用损失的索赔。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰质量)基础知识","建筑工程",0]