[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272978":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1272978,859,2,"多选题","当事人对建设工程付款时间没有约定或者约定不明的，下列时间视为应付款时间（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","建设工程已实际交付的，为交付之日",true,{"key":16,"text":17,"correct":14},"B","建设工程没有交付的，为提交竣工结算文件之日",{"key":19,"text":20,"correct":14},"C","建设工程未交付，工程价款也未结算的，为当事人起诉之日",{"key":22,"text":23,"correct":24},"D","建设工程竣工之日",false,{"key":26,"text":27,"correct":24},"E","以上四项均对","ABC","当事人对建设工程付款时间没有约定或者约定不明的，应付款时间为：①建设工程已实际交付的，为交付之日；②建设工程没有交付的，为提交竣工结算文件之日；③建设工程未交付，工程价款也未结算的，为当事人起诉之日。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰质量)基础知识","建筑工程",0]