[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272876":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1272876,859,2,"多选题","下列选项中，属于施工现场临时用电组织设计的内容的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","负荷计算",true,{"key":16,"text":17,"correct":14},"B","设计配电系统",{"key":19,"text":20,"correct":14},"C","设置防雷装置",{"key":22,"text":23,"correct":24},"D","设置垂直运输通道",false,{"key":26,"text":27,"correct":14},"E","选择变压器","ABCE","施工现场临时用电组织设计的内容的有负荷计算，设计配电系统，设置防雷装置，选择变压器。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰质量)基础知识","建筑工程",0]