[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272862":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1272862,859,2,"多选题","在做基准点线移交时，哪些基准点（线）需要做书面移交（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","主控线",true,{"key":16,"text":17,"correct":14},"B","中轴线",{"key":19,"text":20,"correct":14},"C","基准点",{"key":22,"text":23,"correct":24},"D","吊顶标高线",false,{"key":26,"text":27,"correct":24},"E","1m线","ABC","做基准点线移交时，主控线、中轴线、基准点需要做书面移交。",{"id":6,"name":31,"category":32,"favorite":33},"(装饰质量)基础知识","建筑工程",0]