[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272684":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1272684,859,1,"单选题","建设工程施工合同履行过程中因设计变更等因素导致工程量发生变化应及时办理（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程变更",false,{"key":16,"text":17,"correct":18},"B","工程量签证",true,{"key":20,"text":21,"correct":14},"C","设计变更",{"key":23,"text":24,"correct":14},"D","工程量变更","建设工程施工合同履行过程中因设计变更等因素导致工程量发生变化应及时办理工程量签证。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)基础知识","建筑工程",0]