[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272677":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1272677,859,1,"单选题","以下不属于影响工期因素中社会因素的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","外单位临近工程施工干扰",false,{"key":16,"text":17,"correct":14},"B","节假日交通、市容整顿的限制",{"key":19,"text":20,"correct":14},"C","临时停水、停电、断路",{"key":22,"text":23,"correct":24},"D","不明的水文气象条件",true,"影响工期因素中社会因素有：①外单位临近工程施工干扰、②节假日交通、市容整顿的限制、③临时停水、停电、断路。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)基础知识","建筑工程",0]