[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272628":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1272628,859,1,"单选题","下列哪一项不属于建筑施工企业可以顺延工程工期，并有权要求赔偿停工、窝工等损失的理由（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包方未按照约定的时间和要求提供原材料",false,{"key":16,"text":17,"correct":14},"B","发包方未按约定提供设备",{"key":19,"text":20,"correct":14},"C","发包方或总包单位未按时提供场地",{"key":22,"text":23,"correct":24},"D","发包方未按约定提供施工许可证",true,"有书面记录的下列情形，施工单位可以主张工期顺延（1）建设单位未按照约定提供图纸及开工条件。（2）建设单位未按照约定支付预付款、进度款，致使施工不能正常进行。（3）建设单位指定的代表未按照约定提供指令、批准，致使施工不能正常进行。（4）设计变更和工程量增加。（5）一周内，非施工单位原因停水、停电、停气造成停工累计超过8小时。（6）发生不可抗力事件。（7）隐蔽工程在隐蔽前，施工企业发出检查通知，建设单位未及时检查。（8）建设单位未按照约定时间和要求提供原材料、设备、场地等。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)基础知识","建筑工程",0]