[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272627":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1272627,859,1,"单选题","建设工程经竣工验收合格的，竣工日期应为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","合同约定的竣工日期",false,{"key":16,"text":17,"correct":14},"B","业主单方面下发的竣工日期",{"key":19,"text":20,"correct":21},"C","竣工验收合格之日",true,{"key":23,"text":24,"correct":14},"D","竣工报告提交日期（发包人未拖延验收）","建设工程经竣工验收合格的，竣工日期应为竣工验收合格之日。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)基础知识","建筑工程",0]