[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272617":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1272617,859,1,"单选题","下列不属于工程量索赔的必要条件有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位不同意签证或不完全签证",false,{"key":16,"text":17,"correct":14},"B","在合同约定期限内提出",{"key":19,"text":20,"correct":14},"C","证据事实确凿、充分",{"key":22,"text":23,"correct":24},"D","应有相应的单价及总价",true,"索赔条件1.发包人违反合同给承包人造成时间和费用的损失.2.因工程变更（含设计变更，发包人提出的工程变更，监理工程师提出的工程变更，以及承包人提出并经监理工程师批准的变更）造成时间和费用的损失.3.发包人提出提前完成项目或缩短工期而造成承包人的费用增加.4.发包人延期支付期限造成承包人的损失.5.非承包人的原因导致工程的暂时停工.6.物价上涨，法规变化及其他.二.前提条件1.与合同对照，事件造成了承包人工程项目成本的额外支出，或直接工期损失.2.造成费用增加或工期损失的原因，按合同约定不属于承包人的行为责任或风险责任.3.承包人按合同规定的程序和时间提交索赔意向通知和索赔报告.",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)基础知识","建筑工程",0]