[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272609":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1272609,859,1,"单选题","因（ ）致使工程中途停建、缓建的，发包方应当采取措施弥补或者减少损失，赔偿建筑施工企业因此造成的停工、窝工、倒运、机械设备调迁、材料和构件积压等损失和实际费用。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人原因",true,{"key":16,"text":17,"correct":18},"B","总包方原因",false,{"key":20,"text":21,"correct":18},"C","设计方原因",{"key":23,"text":24,"correct":18},"D","监理单位原因","因发包人原因致使工程中途停建、缓建的，发包方应当采取措施弥补或者减少损失，赔偿建筑施工企业因此造成的停工、窝工、倒运、机械设备调迁、材料和构件积压等损失和实际费用。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)基础知识","建筑工程",0]