[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272594":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1272594,859,1,"单选题","下列选项不正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","隐蔽工程在隐蔽以前，承包人应当通知发包人检查。发包人没有及时检查的，承包人可以顺延工程日期，并有权要求赔偿停工、窝工等损失",false,{"key":16,"text":17,"correct":14},"B","建设工程竣工后，发包人应当根据施工图纸及说明书、国家颁发的施工验收规范和质量检验标准及时进行验收。验收合格的，发包人应当按照约定支付价款，并接收该建设工程",{"key":19,"text":20,"correct":14},"C","建设工程竣工经验收合格后，方可交付使用；未经验收或者验收不合格的，不得交付使用",{"key":22,"text":23,"correct":24},"D","因建设工程超过设计使用年限造成人身和财产损害的，承包人应当承担损害赔偿",true,"如果该建设工程已过合理使用期限的，原则上不允许继续使用，用户继续使用后，因该建设工程造成的人身、财产损害的，承包人不承担损害赔偿责任。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)基础知识","建筑工程",0]