[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272515":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1272515,859,1,"单选题","内墙抹灰施工工艺的流程是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基层清理→弹线找规矩→做灰饼、冲筋→做阳角护角→抹底层灰→抹中层灰→抹阳台板、踢脚板（或墙裙）→抹面层灰→清理",true,{"key":16,"text":17,"correct":18},"B","弹线找规矩→基层清理→做灰饼、冲筋→做阳角护角→抹底层灰→抹中层灰→抹阳台板、踢脚板（或墙裙）→抹面层灰→清理",false,{"key":20,"text":21,"correct":18},"C","弹线找规矩→基层清理→做阳角护角→做灰饼、冲筋→抹底层灰→抹中层灰→抹阳台板、踢脚板（或墙裙）→抹面层灰→清理",{"key":23,"text":24,"correct":18},"D","基层清理→弹线找规矩→做阳角护角→做灰饼、冲筋→抹底层灰→抹中层灰→抹阳台板、踢脚板（或墙裙）→抹面层灰→清理","内墙抹灰施工工艺的流程是基层清理→弹线找规矩→做灰饼、冲筋→做阳角护角→抹底层灰→抹中层灰→抹阳台板、踢脚板（或墙裙）→抹面层灰→清理。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)基础知识","建筑工程",0]