[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272446":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1272446,859,1,"单选题","水磨石机更换新磨石后，应先在废水磨石地坪上或废水泥制品表面磨（ ），待金刚石切削刃磨出后，再投人工作面作业。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.5h",false,{"key":16,"text":17,"correct":14},"B","0.5~1h",{"key":19,"text":20,"correct":21},"C","1~2h",true,{"key":23,"text":24,"correct":14},"D","2.5~3h","水磨石机更换新磨石后，应先在废水磨石地坪上或废水泥制品表面磨1~2h，待金刚石切削刃磨出后，再投人工作面作业。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)基础知识","建筑工程",0]