[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272396":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1272396,859,1,"单选题","在建筑施工中，水准点埋设深度至少要在冻土线以下（ ）确保稳定性。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.2m",false,{"key":16,"text":17,"correct":14},"B","0.3m",{"key":19,"text":20,"correct":21},"C","0.5m",true,{"key":23,"text":24,"correct":14},"D","0.6m","水准点的设置应满足下列基本要求：水准点的数目应不少于3个，以便检核；水准点多设置在沉降变形区以外，距沉降观测点不应大于100m，观测方便，且不受施工影响的地方；为防止冰冻影响，水准点埋设深度至少要在冰冻线以下0.5m。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)基础知识","建筑工程",0]