[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272368":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1272368,859,1,"单选题","施工测量放线准备工作范围不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","图纸准备",false,{"key":16,"text":17,"correct":14},"B","工具准备",{"key":19,"text":20,"correct":14},"C","人员准备",{"key":22,"text":23,"correct":24},"D","材料准备",true,"施工测量放线准备工作范围包括：图纸准备、工具准备、人员准备。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)基础知识","建筑工程",0]