[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272351":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1272351,859,1,"单选题","为保证不受其他因素影响，上、下钢线每（ ）层一个固定支点，水平钢线每（ ）m一个固定支点。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2，15",false,{"key":16,"text":17,"correct":14},"B","1，10",{"key":19,"text":20,"correct":14},"C","3，15",{"key":22,"text":23,"correct":24},"D","2，10",true,"通常是由土建施工单位提供基准线（如500mm标高线，通常称为50线）及轴线控制点，但是由于土建施工允许误差较大，所以不能完全依靠土建水平基准线，必须由基准轴线和水准点重新测量，并校正复核。按土建提供的中心线、水平线、进出位线、50线以及窗台板上皮距水平线的距离，经幕墙安装放线技术人员复测后，放钢线。为保证不受其他因素影响，上、下钢线每2层一个固定支点，水平钢线每10m一个固定支点。",{"id":6,"name":27,"category":28,"favorite":29},"(装饰质量)基础知识","建筑工程",0]