[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272149":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1272149,858,2,"多选题","以下属于施工过程阶段质量控制的内容是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","作业技术交底",true,{"key":16,"text":17,"correct":18},"B","施工组织设计（质量计划）的审查",false,{"key":20,"text":21,"correct":14},"C","中间产品质量控制",{"key":23,"text":24,"correct":14},"D","分部、分项工程质量验收",{"key":26,"text":27,"correct":14},"E","工程变更的审查","ACDE","施工组织设计（质量计划）的审查是施工准备阶段质量控制的内容。",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)专业管理实务 岗位知识","建筑工程",0]