[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272099":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1272099,858,2,"多选题","分部（子分部）工程质量竣工验收的单位有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","分包单位",false,{"key":16,"text":17,"correct":18},"B","勘察单位",true,{"key":20,"text":21,"correct":18},"C","施工单位",{"key":23,"text":24,"correct":18},"D","设计单位",{"key":26,"text":27,"correct":18},"E","监理单位","BCDE","8.0.3分部（子分部）工程验收应由总监理工程师或建设单位项目负责人组织勘察、设计单位及施工单位的项目负责人、技术质量负责人，共同按设计要求和本规范及其他有关规定进行。",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)专业管理实务 岗位知识","建筑工程",0]