[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272096":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1272096,858,2,"多选题","质量计划应包括下列内容（ ）等。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","编制思路",false,{"key":16,"text":17,"correct":18},"B","工程概况及施工条件分析",true,{"key":20,"text":21,"correct":18},"C","质量总目标及其分解目标",{"key":23,"text":24,"correct":18},"D","质量管理组织机构和职责",{"key":26,"text":27,"correct":18},"E","施工准备及资源配置计划","BCDE","GB\u002FT19000-2008中对“质量计划”的定义是：“对特定的项目、产品或合同规定由谁及何时应使用哪些程序和相关资源的文件”。编制依据；质量目标；组织机构；质量控制及管理组织协调的系统描述；必要的质量控制手段，施工过程、服务、检验和试验程序及与其相关的支持性文件；确定关键过程和特殊过程及作业指导书；与施工阶段相适应的检验、试验、测量、验证要求；更改和完善质量计划的程序。",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)专业管理实务 岗位知识","建筑工程",0]