[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1272048":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1272048,858,2,"多选题","饰面板（砖）工程应对下列隐蔽工程项目进行验收（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","基层的强度",false,{"key":16,"text":17,"correct":18},"B","预埋件（或后置预埋件）",true,{"key":20,"text":21,"correct":18},"C","连接节点",{"key":23,"text":24,"correct":18},"D","防水层",{"key":26,"text":27,"correct":14},"E","变形缝","BCD","饰面板（砖）工程应对下列隐蔽工程项目进行验收：1预埋件〈或后直埋件）。2连接节点。3防水层。",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)专业管理实务 岗位知识","建筑工程",0]