[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271936":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1271936,858,2,"多选题","地下防水工程的施工，应建立各道工序的（ ）的制度，并有完整的检查记录。工程隐蔽前，应由施工单位通知有关单位进行验收，并形成隐蔽工程验收记录未经监理单位或建设单位代表对上道工序的检查确认，不得进行下道工序的施工。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","自检",true,{"key":16,"text":17,"correct":18},"B","互检",false,{"key":20,"text":21,"correct":14},"C","交接检",{"key":23,"text":24,"correct":14},"D","专职人员检查",{"key":26,"text":27,"correct":18},"E","监理工程师","ACD","地下防水工程的施工，应建立各道工序的自检，交接检，专职人员检查的制度，并有完整的检查记录。工程隐蔽前，应由施工单位通知有关单位进行验收，并形成隐蔽工程验收记录未经监理单位或建设单位代表对上道工序的检查确认，不得进行下道工序的施工",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)专业管理实务 岗位知识","建筑工程",0]