[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271919":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1271919,858,2,"多选题","灰土地基施工过程中应检查（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","分层铺设的厚度",true,{"key":16,"text":17,"correct":14},"B","夯实时加水量",{"key":19,"text":20,"correct":14},"C","夯压遍数",{"key":22,"text":23,"correct":14},"D","压实系数",{"key":25,"text":26,"correct":27},"E","灰土的密度",false,"ABCD","4.3.2施工过程中必须检查分层厚度、分段施工时搭接部分的压实情况、加水量、压实遍数、压实系数。",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)专业管理实务 岗位知识","建筑工程",0]