[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1271915":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1271915,858,2,"多选题","沉降观测点的设置宜在下列部位（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建筑物的四角、大转角处",true,{"key":16,"text":17,"correct":18},"B","沿外墙角10-15m处",false,{"key":20,"text":21,"correct":14},"C","不同地基基础及地质条件差异处",{"key":23,"text":24,"correct":18},"D","窗台下",{"key":26,"text":27,"correct":14},"E","上部荷载不同处，沉降缝两侧","ACE","沉降观测点的设置宜在下列部位建筑物的四角、大转角处，不同地基基础及地质条件差异处，上部荷载不同处，沉降缝两侧。观测点通常会建在建筑工程上，且横向与纵向相对称，他们之间的最佳距离在20m左右，平均布置在建筑工程四周。",{"id":6,"name":31,"category":32,"favorite":33},"(土建质量)专业管理实务 岗位知识","建筑工程",0]